Land compensation under the National Highways Act

In short: land for national highways is acquired under the National Highways Act, 1956. The competent authority fixes compensation under Section 3G. A landowner who does not accept the amount can seek arbitration by an arbitrator appointed by the Central Government, and the arbitral award can be challenged in court under the Arbitration and Conciliation Act.

The stages of acquisition

  1. Section 3A: notification of the intention to acquire the land.
  2. Section 3C: objections can be filed within 21 days of the notification.
  3. Section 3D: declaration of acquisition; the land then vests in the Central Government.
  4. Section 3G: the competent authority determines the compensation.
  5. Section 3H: the amount is deposited and paid to the persons entitled.

If the compensation is not acceptable

Under Section 3G(5), either side can ask for the amount to be decided by an arbitrator appointed by the Central Government. The award can be challenged under Section 34 of the Arbitration and Conciliation Act, 1996. In Union of India v. Tarsem Singh (2019) the Supreme Court held that solatium and interest are payable on such acquisitions as under the general land acquisition law.

Disputes over who should be paid

Where ownership is disputed, for example between original holders and persons who bought the land after the Section 3D declaration, the competent authority decides the claim, and the High Court can be approached by writ in suitable cases.

Documents usually needed

  • Khatauni and other revenue records
  • The Section 3A and 3D notifications
  • The award of the competent authority
  • Sale deeds, inheritance documents and bank details

This page gives general information about the law and procedure. It is not legal advice and does not create an advocate and client relationship. Please read the disclaimer.